First Well
The river water source was abandoned in 1892 when the City drilled its first deep well. This well used an air lift pump that literally blew the water up from 190 feet below the surface by means of air pressure. This well, No. 1, was originally drilled to 1381 feet but later was deepened to 2235 feet.
By 1895 wells No. 2, No. 3, and No. 4 were drilled and supplied Aurora’s average demand of 1.96 mgd. Eight additional deep wells were drilled from 1911 to 1929 to meet the growth of Aurora.
Building New Water Works
The next major water works project began in 1933 by securing WPA assistance. The project included a 1.5-million-gallon water tower located on Hill Avenue (demolished in December 2013), drilling of Aurora’s 13th well (which was named Well No. 12A), construction of a 4-million-gallon reservoir, and construction of a Main Pumping Station capable of pumping 9 million gallons of water a day. This, along with several miles of 12, 14, and 16-inch water mains, were completed in 1935 for $505,000.
With the growth of Aurora’s west side, a 1.5-million-gallon water tower was constructed in 1964. Additional deep wells were drilled as needed for supply. In 1976 a 1.5-million-gallon hydro pillar was constructed in the northeast section of Aurora, which separated the distribution system into two pressure zones. Additionally, in 1976 a booster pump station, a deep well, and two 1-million-gallon ground storage tanks were constructed to satisfy the fire flow requirements of the Westfield Fox Valley Shopping Center.
Southeast Standpipe & Booster Station
In 1987, in anticipation of the rapid growth of the southeast section of the City, the 5-million-gallon Southeast Standpipe and Booster Station were completed.
New Study for Water Supply & Distribution
Shortly before that, in 1986, City officials authorized Crawford, Murphy, and Tilly, Inc. (CMT), Consulting Engineers, Springfield, Illinois, to perform an engineering study of Aurora’s water supply and distribution system. This was done to investigate water supply alternatives to meet the City’s long-term needs, and to achieve compliance with federal radium standards having a deadline of July 1, 1990.
Water Master Plan
CMT completed the original Water Master Plan in 1987, and was subsequently commissioned to design a new River Intake Facility and Water Treatment Plant (WTP), as part of a $40 million water works improvement program. At that time, it was Aurora’s largest public works project. The WTP was the largest single construction project, with a cost of $19.76 million.
In April 1992, the WTP was placed in operation, and for the first time in approximately 100 years, Aurora was again drawing upon the Fox River for its municipal water supply, as well as from three new shallow wells and previously existing deep wells. The WTP treatment processes includes lime softening (to remove hardness), coagulation, recarbonation (to reduce pH after softening to a more stable level), high-rate filtration, fluoridation, and disinfection.
Water Master Plan Update
During the 1990s, Aurora’s growth continued. In 1998, CMT completed a Water Master Plan Update. This eventually led to the WTP Expansion, which was completed in 2002, and provided one additional “Claricone” softening/coagulation unit, additional high-rate filters, and two new 1.13-million-gallon clearwells to provide additional contact time for disinfection and finished water storage capacity.
Additional Storage
Additional wells and storage facilities have also been constructed. In 2003, the new four-million-gallon Barnes Road Standpipe was completed, and an adjacent booster station was placed in operation in 2006. In 2005, a 1.5-million-gallon storage tank was constructed near Phillips Park, to replace the aging Hill Avenue Elevated Tank.
Today, the City has a total of 16 deep and six shallow wells, and 17.5 million gallons of operational distribution system storage tank capacity.